Communications example

Stakeholder Name Role Information Timeframe Media Responsible for Updates Responsible for Delivery
Carol Anderson Project Sponsor Summary project status 1st each month e-mail Team James White (PM)
Critical risks and issues Weekly Dashboard James White (PM) James White (PM)
Budget & timeline performance 1st each month Dashboard James White (PM) James White (PM)
James White Project Manager Detailed project status Weekly Team status system Tean Team status system
All risks and issues Weekly Team status system Team Team status system
Resource, supplier, procurement budget & timeline performance e/o week e-mail Team Finance Matrix
Sam Dean Safety Auditor Level of safety compliance of all deliverables produced 1st each month 1st each month Quality Manager Quality Manager