Chat with us, powered by LiveChat Chapter12-BudgetPlanning.pptx - STUDENT SOLUTION USA

Budget Planning

This work is licensed under a

(CC-BY).

Project Management

Chapter 12: Budget Planning

1

Budget Management

Importance

Estimating costs to compare and select

Methods of Estimating

Managing the Budget

Budget timeline

Budget variances

This work is licensed under a

(CC-BY).

Project Management

Chapter 12: Budget Planning

Importance of budget planning

Cost is one of the three project constraints

A budget is a plan or forecast

Cost management also includes tracking and managing variances from the planned expenditures

Detailed estimates are important

This work is licensed under a

(CC-BY).

Project Management

Chapter 12: Budget Planning

Estimating costs to compare and select projects

Payback, rate of return or NPV (or combine them)

Need accurate numbers but must balance with the cost of getting more accurate estimates

This work is licensed under a

(CC-BY).

Project Management

Chapter 12: Budget Planning

Estimating methods

Analogous estimate

Find a similar project or task and assume this one will be the same or similar

The more experience the estimator has, the better this works

Learn from each project

DPCI (Darnell-Preston Complexity Index) can help with benchmarking

Parametric estimate

Parameters such as number of square feet for a building; number of kitchens, bathrooms, etc. for a house.

Bottom-up estimating

Estimate each item or task and add them together

Generally more accurate but takes more effort to create

This work is licensed under a

(CC-BY).

Project Management

Chapter 12: Budget Planning

Estimating Guidelines

Don’t gold-plate: estimate what you expect, and meet that estimate.

This work is licensed under a

(CC-BY).

Project Management

Chapter 12: Budget Planning

Managing the Budget

Cash flow

Make a plan of WHEN the outflows will occur, and ensure that the money is available on time

Contingency reserves

For unexpected expenses that arise during the project

There are almost always some surprises, but can’t predict at the start what it will be

Project Manager does not allocate to the sub-projects but manages it centrally

Can be spent and still be within the original project budget

Management Reserves

For scope changes

Not likely to be spent; not part of project baseline

This work is licensed under a

(CC-BY).

Project Management

Chapter 12: Budget Planning

Reporting Progress: Earned value management

Budgeted Cost of work Scheduled BCWS Detailed estimates for each activity in the project
Planned Value PV Total budgeted cost as of a certain date in the project
Earned Value EV Budgeted cost of the completed work as of a certain date in the project
Actual Cost AC Actual cost of the completed work as of a certain date in the project
Budget at Completion BAC Total budgeted costs for the entire project

This work is licensed under a

(CC-BY).

Project Management

Chapter 12: Budget Planning

Project Cost Chart

BAC

This work is licensed under a

(CC-BY).

Project Management

Chapter 12: Budget Planning

Budget BaselineFebruaryMarchAprilMayJuneJuly100001200022000300004000045000

Budget Baseline and Project Cost Chart

The project budget is usually shown graphically, illustrating the cumulative planned spending.

Typical shape for the budget curve is s-shaped, with less spending at the beginning and end of the project.

Add the periodic expenditures on a regular basis to create the Project Cost Chart.

This work is licensed under a

(CC-BY).

Project Management

Chapter 12: Budget Planning

Project Cost Chart (up to May)

BAC

AC

This work is licensed under a

(CC-BY).

Project Management

Chapter 12: Budget Planning

Actual ExpendituresFebruaryMarchAprilMayJuneJuly500070003000035000Budget BaselineFebruaryMarchAprilMayJuneJuly100001200022000300004000045000

Schedule Variance: SV

Difference between planned and actual progress

SV=EV-PV

Positive value: project is ahead of schedule

Zero: project is on-time

Negative: project is behind schedule

This work is licensed under a

(CC-BY).

Project Management

Chapter 12: Budget Planning

Cost Variance: CV

The difference between the earned value and the actual cost is the cost variance:

CV=EV-AC

If positive, you are achieving more than you predicted for the money

If zero, you are right on the plan

If negative, you are achieving less than you predicted for the money

This work is licensed under a

(CC-BY).

Project Management

Chapter 12: Budget Planning

Schedule Performance Index: SPI

Compares progress on the scope to spending:

SPI = EV/PV

SPI less than one indicates the project is behind schedule

SPI of one is right on schedule

SPI greater than one the project is ahead of schedule

This work is licensed under a

(CC-BY).

Project Management

Chapter 12: Budget Planning

Cost Performance Index: CPI

Compares the budget spent to date with progress to date:

CPI=EV/AC

A value greater than one: under budget

Equal to one: on budget

Less than one: overspending the budget

This work is licensed under a

(CC-BY).

Project Management

Chapter 12: Budget Planning

Estimated Cost to Complete the Project: ETC

Formula to use depends on what the PM expects with regard to future project costs and whether the original budget assumptions remain valid

This work is licensed under a

(CC-BY).

Project Management

Chapter 12: Budget Planning

ETC if past variances are not expected to continue:

ETC = BAC – EV

This work is licensed under a

(CC-BY).

Project Management

Chapter 12: Budget Planning

ETC if past variances are expected to continue at the same level

ETC = (BAC – EV)/CPI

This work is licensed under a

(CC-BY).

Project Management

Chapter 12: Budget Planning

Estimated Final Project Cost: EAC

EAC = ETC + AC

This work is licensed under a

(CC-BY).

Project Management

Chapter 12: Budget Planning

Budget Timeline

Contractual agreements often require partial payments

Prepare a schedule, based on contractual and other expenditure requirements

This work is licensed under a

(CC-BY).

Project Management

Chapter 12: Budget Planning

Budget Management Summary

Cost estimations may be used to choose between options

Managing the budget includes

Estimating costs and setting a budget

Determining when the budgeted costs should occur

Tracking expenditures

Managing variances between the budget and the expenditures

Methods of Estimating

Analogous, Parametric, Bottom-up

Managing the Budget

Budget timeline

Budget variances

This work is licensed under a

(CC-BY).

Project Management

Chapter 12: Budget Planning

Budget Management Summary (continued)

Budgeting and Cost Management are important activities for project managers

There are several methods for estimating the costs

Estimated costs may be used to choose between options

Project progress and budget management are closely related and can be managed with indices: BCWS, PV, SV, AC, CV, SPI, CPI, ETC, BAC and EAC

Contingency funds allow for the unexpected

Reporting to the team and to management are important components in budget management

This work is licensed under a

(CC-BY).

Project Management

Chapter 12: Budget Planning

Questions?

This work is licensed under a

(CC-BY).

Project Management

Chapter 12: Budget Planning

23

image1.png

error: Content is protected !!