Problem Earned-value analysis. A project budget calls for the following expenditures:Task Date Budgeted Amount:Build forms April 1$10,000 Pour foundation April 1$50,000 May 1$100,000Frame walls May 1$30,000 June 1$30,000Remaining tasks July 1 and...